EcoGraf flags 20% Phase 1 capacity uplift for Epanko graphite project to 87,600 tpa

PUBT·09/24/2026 16:17:18
EcoGraf flags 20% Phase 1 capacity uplift for Epanko graphite project to 87,600 tpa
  • EcoGraf flagged a value-engineering review for its Epanko graphite project that lifts Phase 1 nominal capacity 20% to 87,600 tpa.
  • Estimated C1 costs for the first 10 years fell 5.8% versus the February 2026 BFS to about USD 512.3 per tonne.
  • The February 2026 BFS case of 73,000 tpa remains the base for development funding, with the 87,600 tpa case post-FID.
  • Preliminary work indicated the 20% uplift needs no change to the BFS layout, with about USD 12 million in incremental capex.
  • Higher output could support a single 25,000 tpa HFfree battery anode material plant, backing expansion plans in Europe, Asia, the US.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. EcoGraf Limited published the original content used to generate this news brief via EQS News (Ref. ID: corporate_2405140_de) on September 24, 2026, and is solely responsible for the information contained therein.