Yooshin Engineering extends contract end date for Gyeongju Eco Energy waste facility build to Oct. 30, 2026

PUBT·09/30/2026 08:00:01
Yooshin Engineering extends contract end date for Gyeongju Eco Energy waste facility build to Oct. 30, 2026
  • Yooshin Engineering corrected its sales and supply contract filing, extending the end date to 2026-10-30 from 2026-09-30.
  • Change reflects delays in administrative procedures for final completion approval, despite construction completion.
  • Contract covers construction of a comprehensive waste treatment facility in Gyeongju for Gyeongju Eco Energy.
  • Total contract value KRW 40.04 billion, equal to 11.79% of 2024 consolidated revenue.
  • Cumulative collections reached KRW 36.3 billion, or 90.65% of the contract amount.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Yooshin Engineering Corporation published the original content used to generate this news brief via DART, the regulatory disclosure system operated by the South Korea Financial Supervisory Service (FSS) (Ref. ID: 20260930900641), on September 30, 2026, and is solely responsible for the information contained therein.