Applied Digital Completes Base-Build Commissioning For First 75 MW Of Initial 150 MW Data Center Building At Polaris Forge 2 In Harwood, North Dakota

Benzinga·11/24/2026 13:06:02

On-schedule Polaris Forge 2 milestone establishes the foundation for the next 50 MW of customer deliveries, reinforcing repeatable execution against more than $41 billion in contracted base-term lease revenue

DALLAS, Nov. 24, 2026 (GLOBE NEWSWIRE) -- Applied Digital (NASDAQ:APLD), a U.S. based AI data center infrastructure company specializing in the design, development, ownership and operation of large-scale, purpose-built campuses serving hyperscale off-takers under long-term contracts, today announced it has completed base-build commissioning for the first 75 MW of its initial 150 MW data center building at Polaris Forge 2 in Harwood, North Dakota. Within this phase, the Company has completed the integrated fit-out of the first 25 MW data hall and achieved Ready for Service on schedule.