Kenmare Resources Delays Commissioning of Upgraded Wet Concentrator Plant

MT Newswires·12/17/2025 04:20:34
Listen to the news
04:20 AM EST, 12/17/2025 (MT Newswires) -- Kenmare Resources (KMR.L) expects the wet concentrator plant A at its Moma titanium minerals mine in Mozambique to achieve nameplate capacity of 3,500 tonnes per hour in the first quarter of 2026, not by the end of 2025. The London-listed titanium minerals and zircon producer is delaying the full commissioning of the upgraded plant due to issues mainly related to slimes management, according to a Wednesday filing. The new schedule is not expected to increase the estimated capital cost of the upgrade project, which remains at $341 million.