-+ 0.00%
-+ 0.00%
-+ 0.00%

International Tower Hill Mines releases corporate presentation on Livengood gold project development

PUBT·04/24/2026 11:02:10
Listen to the news
International Tower Hill Mines releases corporate presentation on Livengood gold project development
  • International Tower Hill outlined plan to advance Livengood Gold Project in Alaska toward production, positioning asset as one of largest undeveloped gold projects in United States.
  • Presentation highlighted 9 million oz proven and probable reserves, measured and indicated resources of 13.6 million oz.
  • 2023 pre-feasibility study assumptions included initial capex of USD 1.93 billion, life-of-mine AISC of about USD 1,171/oz.
  • Mine plan targeted 21-year life with 6.4 million oz production, average annual output of 388,600 oz in years 1-5.
  • Company cited USD 118 million financing completed in January 2026 to support feasibility study work, permitting, drilling, antimony test work.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. International Tower Hill Mines Ltd. published the original content used to generate this news brief on April 24, 2026, and is solely responsible for the information contained therein.