Pembina Pipeline invests $570 million in Heartland NGL extraction plant expansion

PUBT·05/25/2026 11:00:22
Listen to the news
Pembina Pipeline invests $570 million in Heartland NGL extraction plant expansion
  • Pembina Pipeline sanctioned the Heartland Extraction Plant, a 750 MMcf/d straddle facility tied to its Yellowhead Pipeline NGL extraction rights.
  • Project cost estimated at about $570 million; targeted in-service date set for late 2029.
  • Long-term deal to supply Dow with ethane from late 2029; volumes ramp to 22,500 bpd by end-2030.
  • Amended separate agreement lifts Dow ethane supply to 35,000 bpd starting with the Path2Zero start-up expected in 2029.
  • Total ethane supply commitment to Dow rises to 57,500 bpd, up 15% from the original 50,000 bpd agreement.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Pembina Pipeline Corporation published the original content used to generate this news brief via Business Wire (Ref. ID: 20260525507282) on May 25, 2026, and is solely responsible for the information contained therein.