Aarsleff wins Energinet design-build contract for Bornholm Energy Island land facilities worth DKK 3.7 billion

PUBT·07/17/2026 08:16:30
Listen to the news
Aarsleff wins Energinet design-build contract for Bornholm Energy Island land facilities worth DKK 3.7 billion
  • Per Aarsleff Holding won a design-and-build contract from Energinet for land facilities for the Bornholm Energy Island project.
  • Contract value totals DKK 3.7 billion.
  • Facilities will connect future Baltic Sea offshore wind output to the Danish grid plus Germany, with sites on Bornholm and in Høje Taastrup.
  • Design starts Aug. 1; initial earthworks and concrete work expected around the 2027/28 year-end period.
  • Handover is expected in 2030 for the Bornholm facility, 2031 for the Høje Taastrup facility.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Per Aarsleff Holding A/S published the original content used to generate this news brief on July 17, 2026, and is solely responsible for the information contained therein.