Transelec rebuilds Coquimbo transmission line after flooding washes out 10 towers

PUBT·08/04/2026 12:26:46
Listen to the news
Transelec rebuilds Coquimbo transmission line after flooding washes out 10 towers
  • Transelec is rebuilding the Maitencillo–Las Compañías transmission line in Chile’s Coquimbo region following flood damage from a severe storm system.
  • Rising waters in the Quebrada de Los Choros river, near Trapiche, destroyed about 10 transmission structures, disrupting a key backup link in the national grid.
  • Power supply in the affected area has been fully restored and delivered to distribution companies, shifting the focus to permanent reconstruction.
  • Work is scheduled to be completed by Aug. 15, following initial access constraints caused by Route 5 Norte closures.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Transelec SA published the original content used to generate this news brief on August 04, 2026, and is solely responsible for the information contained therein.