Gunnison Copper posts investor deck outlining Arizona Gunnison copper cathode project economics and development plan

PUBT·08/06/2026 10:38:22
Listen to the news
Gunnison Copper posts investor deck outlining Arizona Gunnison copper cathode project economics and development plan
  • Gunnison Copper outlined a 2026 PEA for its Arizona Gunnison project, targeting a 21-year open-pit heap-leach SX/EW copper cathode operation.
  • After-tax NPV at 8% of USD 1.96 billion; after-tax IRR 22.5% at USD 4.6/lb copper; initial capex with acid plant USD 1.56 billion.
  • Average annual copper cathode output about 174 million lbs in years 1-15; total recovered copper 3.2 billion lbs; AISC USD 2.05/lb.
  • First copper production shown as 2030/2032; payback period 3.9 years.
  • Presentation flagged U.S. funding pathways, including potential DoE loan programs, DIBC participation, and prior DoE 48C tax credits.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Gunnison Copper Corp. published the original content used to generate this news brief on August 06, 2026, and is solely responsible for the information contained therein.