Oncor places 165-mile Delaware Basin Stage 2 345-kV transmission line in service

PUBT·08/06/2026 12:19:13
Listen to the news
Oncor places 165-mile Delaware Basin Stage 2 345-kV transmission line in service
  • Oncor placed in service its portion of the 165-mile Delaware Basin Stage 2 double-circuit 345 kV transmission line in June.
  • The project is part of a broader buildout to relieve urgent electricity import constraints into far west Texas.
  • ERCOT-endorsed transmission upgrades across southern Dallas-Fort Worth and the I-35 corridor imply over $7 billion of investment during 2026-2034.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Oncor Electric Delivery Company LLC published the original content used to generate this news brief on August 06, 2026, and is solely responsible for the information contained therein.