EnBW completes installation of 64 turbines at 960-MW He Dreiht offshore wind farm

PUBT·08/12/2026 07:05:17
Listen to the news
EnBW completes installation of 64 turbines at 960-MW He Dreiht offshore wind farm
  • EnBW completed installation of all 64 turbines at the 960-megawatt He Dreiht offshore wind farm, using 15-megawatt Vestas units.
  • Technical and electrical commissioning is set for coming weeks; full start-up targeted by late summer.
  • Vestas is investigating damage to a rotor blade that occurred in late July.
  • The project is Germany’s largest offshore wind farm; it is being built without state subsidies.
  • Investment totals EUR 2.4 billion; a partner consortium holds a 49.9% stake.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. EnBW - Energie Baden-Württemberg AG published the original content used to generate this news brief on August 12, 2026, and is solely responsible for the information contained therein.