Nouveau Monde Graphite launches construction at Phase 2 Matawinie mine after FID

PUBT·08/13/2026 11:00:36
Listen to the news
Nouveau Monde Graphite launches construction at Phase 2 Matawinie mine after FID
  • Nouveau Monde Graphite confirmed the financial investment decision for Phase 2 of the Matawinie Mine in Q2 2026, triggering construction.
  • Project spending totaled C$ 33 million by June 30, 2026; committed costs reached C$ 167 million, with work tracking within budget.
  • Québec amended the Matawinie Mine authorization on Aug. 5, lifting permitted annual graphite output to 106,000 tonnes from 100,000 tonnes.
  • Class 3 cost estimate set CAPEX for the 13 ktpy Bécancour Battery Material Plant at C$ 374 million; targeted FID remains H2 2026.
  • Panasonic Energy reiterated potential equity participation at the Bécancour plant FID, consistent with its initial 2024 investment.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Nouveau Monde Graphite Inc. published the original content used to generate this news brief via Business Wire (Ref. ID: 20260813290286) on August 13, 2026, and is solely responsible for the information contained therein.