Keller installs 140 rotary bored piles for Port Talbot electric arc furnace project

PUBT·08/14/2026 11:17:25
Listen to the news
Keller installs 140 rotary bored piles for Port Talbot electric arc furnace project
  • Keller Group is installing 1,350 piles to prepare the Port Talbot site for construction of a new electric arc furnace.
  • Second-phase works started in July, including 140 large-diameter rotary bored piles to depths of up to 36.5 meters.
  • Scope also includes more than 330 CFA piles to depths above 31 meters, supported by more than 200 restricted-access piles.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Keller Group plc published the original content used to generate this news brief on August 14, 2026, and is solely responsible for the information contained therein.