Rompetrol Rafinare invests RON 27 million in 4.8-MW solar plant, 9-MWh storage at Vega refinery

PUBT·08/21/2026 13:16:21
Listen to the news
Rompetrol Rafinare invests RON 27 million in 4.8-MW solar plant, 9-MWh storage at Vega refinery
  • Rompetrol Rafinare will develop a 4.8 MW solar plant at its Vega Ploiești refinery, paired with about 9 MWh of storage.
  • Total investment estimated at nearly RON 27 million, including about RON 7 million from the Modernization Fund.
  • Project deadline set for Dec. 31, 2028; output forecast above 6,200 MWh a year for on-site consumption.
  • Annual CO2 emissions expected to fall by more than 3,800 tons; solar generation seen covering about two-thirds of Vega’s budgeted 2025 electricity use.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Rompetrol Rafinare SA published the original content used to generate this news brief on August 21, 2026, and is solely responsible for the information contained therein.