Silverco targets La Negra mine ramp-up to 2,500 tpd in H1 2027 after tailings filtration upgrade

PUBT·08/24/2026 10:31:16
Listen to the news
Silverco targets La Negra mine ramp-up to 2,500 tpd in H1 2027 after tailings filtration upgrade
  • Silverco outlined a La Negra mine upgrade plan in Mexico, targeting 2,500 tonnes per day nameplate throughput in H1 2027.
  • Filtered tailings conversion remains on schedule for end-Q1 2027 commissioning, aimed at removing a key throughput constraint.
  • Underground fleet renewal orders placed with deliveries slated for Q4 2026 through Q1 2027 to lift mining rates.
  • A 15,000-meter exploration drill program started in mid-July; first assays expected in late Q3 2026.
  • SGS hired for an updated resource estimate and a preliminary economic assessment, with results expected in late Q3 2026.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Silverco Mining Ltd. published the original content used to generate this news brief via Newsfile (Ref. ID: 202608240630NEWSFILECNPR____20260824_311015_1) on August 24, 2026, and is solely responsible for the information contained therein.