Dakota Gold targets 2029 start for Richmond Hill heap-leach gold production in analyst tour presentation

PUBT·08/27/2026 22:58:57
Listen to the news
Dakota Gold targets 2029 start for Richmond Hill heap-leach gold production in analyst tour presentation
  • Dakota Gold outlined a plan to advance the Richmond Hill heap-leach gold project, targeting first production as soon as 2029.
  • Richmond Hill S-K 1300 heap-leachable resource: 3.65 million oz M&I gold, 2.61 million oz inferred gold, 38.1 million oz M&I silver.
  • Combined heap-leach and milled resource: 4.64 million oz M&I gold, 5.06 million oz inferred gold, 47.8 million oz M&I silver.
  • Pre-Feasibility Study targeted for Q4 2026; Feasibility Study targeted for H1 2027.
  • Cash balance of $99 million as of June 30, 2026; described as funded through feasibility.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Dakota Gold Corporation published the original content used to generate this news brief on August 27, 2026, and is solely responsible for the information contained therein.