Solwers unit Finnmap Infra settles E18 Turku ring road dispute with Kreate

PUBT·08/31/2026 08:00:49
Listen to the news
Solwers unit Finnmap Infra settles E18 Turku ring road dispute with Kreate
  • Solwers unit Finnmap Infra reached a settlement with Kreate over an alleged performance breach on the E18 Turku Ring Road project.
  • Both sides will withdraw all claims, lawsuits, counterclaims tied to the dispute, ending the Helsinki District Court case.
  • The dispute included Kreate’s EUR 2.46 million claim filed in February 2025.
  • Finnmap Infra had sought EUR 1.07 million from Kreate in a counterclaim filed in May 2025.
  • Terms are confidential; Solwers said the settlement has no material impact on the group’s financial position or operations.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Solwers Oyj published the original content used to generate this news brief via Cision (Ref. ID: 20260831:BIT:4103:0) on August 31, 2026, and is solely responsible for the information contained therein.