Ximen Mining advances Kenville gold mine construction, targets portal work by end-October 2026

PUBT·09/10/2026 21:45:48
Listen to the news
Ximen Mining advances Kenville gold mine construction, targets portal work by end-October 2026
  • Ximen Mining advanced construction at the Kenville Gold Mine near Nelson, British Columbia, moving into site works ahead of underground development.
  • Liner installation for permitted flood-retention ponds began, with completion targeted by end-September 2026, subject to site conditions.
  • Mines Act authorization covers a new Venango Portal and 1,200 meters of decline development, with groundwater licences already in hand.
  • Portal construction is targeted to start by end-October 2026, subject to remaining preconditions, engineering deliverables, contractors, procurement, and site conditions.
  • Funding options remain under review to support construction and mobilization.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Ximen Mining Corp. published the original content used to generate this news brief via Newsfile (Ref. ID: 202609101745NEWSFILECNPR____20260910_313930_1) on September 10, 2026, and is solely responsible for the information contained therein.