-+ 0.00%
-+ 0.00%
-+ 0.00%

Silver Tiger says El Tigre project stays on track for December 2027 commissioning, first pour

PUBT·09/14/2026 11:05:02
Listen to the news
Silver Tiger says El Tigre project stays on track for December 2027 commissioning, first pour
  • Silver Tiger Metals flagged El Tigre mine construction in Sonora, Mexico remains on track for commissioning and first pour in December 2027.
  • Detailed engineering under the EPCM contract is 65% complete; earthworks for the heap-leach and plant platforms reached 30%.
  • Long-lead procurement finished for the crusher system, stacking equipment, Merrill-Crowe plant, and refinery.
  • Site workforce exceeds 250; 219,000 man-hours logged since construction began.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Silver Tiger Metals Inc. published the original content used to generate this news brief via ACCESS Newswire (Ref. ID: 202609140700ACCESSWRNAPR_____1220404) on September 14, 2026, and is solely responsible for the information contained therein.