Gunnison Copper, Nuton add 3 million tons to Johnson Camp Stage 2 mine plan, securing US$8 million payment

PUBT·09/16/2026 10:02:51
Listen to the news
Gunnison Copper, Nuton add 3 million tons to Johnson Camp Stage 2 mine plan, securing US$8 million payment
  • Gunnison Copper reached a deal with Nuton to revise the Stage 2 mine plan at Arizona’s Johnson Camp Mine.
  • Plan adds about 3 million tons of mineralized material, scheduled to be mined during the 2027-2029 demonstration period.
  • Nuton agreed to pay USD 8 million, with receipt expected in Q4 2026.
  • Company opted not to pursue DOE 48C tax credits that were conditionally awarded in January 2025.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Gunnison Copper Corp. published the original content used to generate this news brief via Newsfile (Ref. ID: 202609160600NEWSFILECNPR____20260916_314551_1) on September 16, 2026, and is solely responsible for the information contained therein.