Keller installs 1,000-plus piles for Viridor Thameside energy recovery project at Tilbury Docks

PUBT·09/16/2026 11:26:40
Listen to the news
Keller installs 1,000-plus piles for Viridor Thameside energy recovery project at Tilbury Docks
  • Keller was selected as principal contractor for foundation works on Viridor’s Thameside Energy Recovery Facility at Tilbury Docks, Essex.
  • More than 1,000 piles were installed using CFA and driven precast methods to support the plant’s heavy structural loads.
  • The facility is designed to process 350,000 tonnes of residual waste a year into electricity, with commercial operations targeted for 2028.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Keller Group plc published the original content used to generate this news brief on September 16, 2026, and is solely responsible for the information contained therein.