Tongyang removes contract end date for KRW 57.78 billion biomass plant EPC order amid renegotiation talks

PUBT·09/30/2026 09:22:13
Listen to the news
Tongyang removes contract end date for KRW 57.78 billion biomass plant EPC order amid renegotiation talks
  • Tongyang revised its disclosure on a KRW 57.78 billion biomass power plant EPC subcontract tied to Lotte E&C.
  • The contract end date was removed from the filing, replacing a previously stated 2026-09-30 completion date.
  • Contract terms, including price, remain under negotiation; an amended agreement will trigger a further corrected disclosure.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Tongyang Inc. published the original content used to generate this news brief via DART, the regulatory disclosure system operated by the South Korea Financial Supervisory Service (FSS) (Ref. ID: 20260930801015), on September 30, 2026, and is solely responsible for the information contained therein.