Woojin I&S revises data center mechanical works contract value to 5.39 billion won

PUBT·10/08/2026 02:32:51
Listen to the news
Woojin I&S revises data center mechanical works contract value to 5.39 billion won
  • Woojin I&S corrected its disclosed single construction contract for a Gasan-dong data center mechanical works project.
  • Contract value revised to KRW 5.39 billion from KRW 5.04 billion, lifting the sales ratio to 3.92% from 3.66%.
  • Project end-date extended to Oct. 30, 2026 from Aug. 30, 2026; start date stays Nov. 17, 2025.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Woojin I&S Co. Ltd. published the original content used to generate this news brief via DART, the regulatory disclosure system operated by the South Korea Financial Supervisory Service (FSS) (Ref. ID: 20261008800228), on October 08, 2026, and is solely responsible for the information contained therein.