Digi Power X secures commitment for US$200 million debt financing for Alabama AI data center project

PUBT·10/13/2026 11:33:33
Listen to the news
Digi Power X secures commitment for US$200 million debt financing for Alabama AI data center project
  • Digi Power X received a commitment letter for US$ 200 million in debt financing for its 40 MW AI data center in Columbiana, Alabama.
  • Goldman Sachs is syndicating the financing, expected to close within 90 days, subject to documentation and lender due diligence.
  • Structure set at a project SPV level, backed by an unsecured corporate guarantee through completion and other limited matters.
  • Proceeds earmarked to complete the Alabama project, support related costs, preserve liquidity, reduce dilution, support additional customer contracts.
  • Construction timeline unchanged, with Phase 1 targeted for December 2026, Phase 2 for March 2027.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Digi Power X Inc. published the original content used to generate this news brief via ACCESS Newswire (Ref. ID: 202610130730ACCESSWRNAPR_____1236162) on October 13, 2026, and is solely responsible for the information contained therein.