Liberty Gold secures long-lead equipment for Black Pine gold project in Idaho

PUBT·10/27/2026 10:01:01
Listen to the news
Liberty Gold secures long-lead equipment for Black Pine gold project in Idaho
  • Liberty Gold secured long-lead equipment fabrication capacity for its wholly owned Black Pine gold project in Idaho.
  • Contracts cover electrical transformers from Nexus Power and gold recovery plant and refinery packages from CGS Associates, reducing construction schedule risk.
  • M3’s infrastructure and processing engineering is approximately 5% complete; NewFields’ heap leach facility engineering is approximately 15% complete.
  • Detailed engineering is targeted for completion in the third quarter of 2027.
  • Construction is targeted to begin in the first half of 2028, subject to permitting approvals and a formal construction decision.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Liberty Gold Corp. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202610270600PRIMZONEFULLFEED9853339) on October 27, 2026, and is solely responsible for the information contained therein.