Eneva secures port site for 690 MW Espírito Santo gas-fired power hub

PUBT·11/03/2026 21:41:22
Listen to the news
Eneva secures port site for 690 MW Espírito Santo gas-fired power hub
  • Eneva secured port-use agreements with Vports at Barra do Riacho, Espírito Santo, for an LNG terminal and thermal power plants.
  • The Espírito Santo hub will be 100%-owned, with site-use rights through December 31, 2046, subject to customary conditions and renewable.
  • The 690-MW Espírito Santo hub is scheduled to begin commercial operations on August 1, 2031.
  • Ceará's 1,659.4-MW hub targets 1,199.4 MW online August 1, 2029, with 460 MW following August 1, 2031.
  • Both hubs have 15-year capacity sales commitments secured in the 2026 capacity reserve auction.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Eneva SA published the original content used to generate this news brief on November 03, 2026, and is solely responsible for the information contained therein.