LS Power Says Permitting, Grid Connections Constrain New US Power Supply

PUBT·11/16/2026 20:00:51
Listen to the news
LS Power Says Permitting, Grid Connections Constrain New US Power Supply
  • Grid connection and permitting bottlenecks, not capital shortages, constrain new U.S. power generation, LS Power CEO Paul Segal told Bloomberg TV.
  • Billions in private capital await projects with permits and financing readiness.
  • Gigawatt-scale gas plants take five years to develop, versus one to two years for data centers, creating a supply-demand timing mismatch.
  • PJM faces increasing capacity shortages as demand rises; Texas remains well supplied following rapid additions of wind, solar and battery storage.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Ls Power Group published the original content used to generate this news brief on November 16, 2026, and is solely responsible for the information contained therein.