  • KEPCO Engineering & Construction extended its Shin-Kori units 5 and 6 reactor-system design contract beyond Nov. 30, 2026.
  • The contract with Doosan Enerbility is valued at KRW 214.78 billion, including value-added tax.
  • Negotiations cover the contract duration and value, with a further correction disclosure planned once changes are finalized.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. KEPCO Engineering & Construction Co. Inc. published the original content used to generate this news brief via DART, the regulatory disclosure system operated by the South Korea Financial Supervisory Service (FSS) (Ref. ID: 20261124800429), on November 24, 2026, and is solely responsible for the information contained therein.